Chinese and Canadian sources impact 40-year license renewal Powerhouse MCKENZIE BRIDGE: Turbines won’t be spinning nor will boaters be launching for a few more years. That’s because refurbishment work at the Carmen-Smith hydro plant has been delayed. In a report delivered to the Eugene Water & Electric Board for their November meeting, the utility’s generation manager Mike McCann noted that design issues and manufacturing at fac-ilities in China were affecting General Electric’s ability to deliver equipment needed for the overhaul of one of...