Make the McKenzie Connection!

Bridge closures delayed a week

** 2/8/13 ** Dates changed again by Lane County Public Works

Bridge closures moved to Feb. 25, 26 & 27

Temporary steel bracing inside bridge9:34 a.m: Earlier this morning it was announced that the Goodpasture covered bridge closures planned for next week, Thursday night, February 14th and Friday night, February 15th have been cancelled and rescheduled for Wednesday night, February 20th, Thursday night, February 21st, and Friday night, February 22nd.  These closures will be from 8:00 p.m. to 5:00 a.m. for three consecutive nights.  These bridge closures will allow workers to remove and replace the floor decking.

The times are the same but the dates are now Feb. 25, 26 & 27.

During the next two weeks, workers will be installing permanent bridge railing and continue painting the bridge siding.

 

McKenzie River Reflections

 

Reader Comments(0)

 
 
Rendered 11/11/2024 11:09